Status of a task comparing actual start and actual end dataes with planned start and planned end dates
Namespace: Autodesk.Navisworks.Api.Timeliner
Assembly: Autodesk.Navisworks.Timeliner (in Autodesk.Navisworks.Timeliner.dll)
Syntax
Visual Basic |
---|
Public Enumeration TaskStatus |
C# |
---|
public enum TaskStatus |
Visual C++ |
---|
public enum class TaskStatus |
Members
Member name | Description | |
---|---|---|
None |
The task has no status
| |
Same |
The planned and actual dates are the same
| |
Before |
The actual dates are before the planned dates
| |
After |
The actual dates are afetr the planned dates
| |
EarlyStartLateFinish |
The actual start date is before the planned start date; the actual end date is after the planned end date
| |
LateStartEarlyFinish |
The actual start date is after the planned start date; the actual end date is before the planned end date
| |
EarlyStart |
The actual start date is before the planned start date; the actual end and planned end dates are the same
| |
LateFinish |
The actual start and planned start dates are the same; the actual end date is after the planned end date
| |
EarlyStartFinish |
The actual start date is before the planned start date; the actual end date is before the planned end date and after the planned start date
| |
LateStartFinish |
The actual start date is after the planned start date and before the planned end date; the actual end date is after the planned end date
| |
ActualOnly |
The task has only actual dates
| |
PlannedOnly |
The task has only planned dates
| |
EarlyFinish |
The actual start date is the same as the planned start date; the actual end date is after the planned start date and before the planned end date
| |
LateStart |
The actual start date is after the planned start date and before the planned end date; the actual end date is the same as the planned end date
|
Remarks
States the relationship between actual dates and planned dates.